Extension        Mission statement        Through announcement for bidding, the ministry of electricity supplying heavy fuel oil for Tasluja power plant        Information department of the ministry of electricity        Only by in-depth and objective reports discussion can be stimulated to address the problems        The representatives of the demonstration and the organization's joint center have met with the ministry        opening Training Course        The investments of Czech Republic in electricity sector        To ……….media channel        PRESS RELEASE        

09-10-2007
The system Supplying electricity for October 2007

The following is a system supplying electricity for October 2007in both Erbil and Sulaimaniya governorates:
*Everyday,both Dukan and Derbandikhan power-production stations shall work from 1:00pm until 1:00am and they shall daily produce power at the rate of 188MW.
*It is scheduled that both Erbil and Sulaimanyia governorates shall be provided with at least 200MW by Iraqi National Power Networks.
*It is decided  that the citizens shall be supplied with power everyday for 6 to 7& half hours  from the above mentioned amount of power in both governorates.
*Local generates shall supply power for 8 hours daily,and their power-distribution schedule shall be coordinated with Regional Electrical-power Networks.
*This system shall be assessed  by the end of  the October2007,then the new system shall be set up for November.
*For the meals before daybreak of last ten nights of holy Ramadhan month  in October,the local generates shall be operated.
* The units of Dukan and Derbandikhan power-stations shall work for 24 hours during the first feast night at 1:00pm,.